Bulk Material Handling and Storage System
Project Name:Coal Handling and Storage System of Huayang (Luoyang) Mengjin Power Plant
Owner:Huayang Mengjin Power Plant
Status:Completed in 2010&2011
Detailed information:

Location:                                   Henan, China
Handling Material:                    Coal
BW of Conveyor:                      1,400mm
Conveying Capacity :               1,500t/h
Coal Dome Diameter:              Φ120m *2
Storage Capacity:                    170,000t *2
Stacker / Reclaimer Capacity: 1,500/1,500t/h